Your IT vendor says the project is 90% done. Should you be happy?
Not so fast.
I’ve heard this update many times:
“We are about 90% done. We’re just finishing a few things.”
But when you ask what is actually left, the answers become less clear.
And that is a problem.
You cannot manage a percentage. You need to manage the work that remains.
Here is one simple thing you can do at your next vendor meeting:
Ask the vendor to list every unfinished item.
For each item, agree on four things:
- What exactly needs to be completed?
- Who is responsible for completing it?
- On what date will it be ready?
- What evidence will show that it is actually finished?
For example, instead of:
“Only 10 errors remain.”
You want something like:
- Error 1: Login fails for a specific user role. Owner: Vendor developer. Due: Thursday. Proof: Successful test.
- Error 2: Report totals are incorrect. Owner: Vendor developer. Due: Friday. Proof: Correct results using agreed test data.
Now you have something you can track, discuss, and verify.
No more guessing what “90% done” means.
Remember: Progress is not a percentage. Progress is work you can verify.
This is just one of the practical techniques I cover in my upcoming course:
How to Get a Late IT Vendor Back on Schedule.
It’s designed for Project Managers, Product Owners, Scrum Masters, and IT Managers who are tired of chasing promises and want to get their projects moving again.
Join the waiting list to be notified when the course launches.